Aizawl, Nov 19 (UNI) Construction of the 45-km Aizawl Western Bypass Road has achieved 33.61% progress, with a government monitoring committee expressing concern over the slow pace of work and urging the contractor to deploy more machinery to expedite construction.
The Special Monitoring Committee on the Aizawl Bypass Road on the western side inspected the ongoing construction on Thursday to assess progress and review issues affecting the project.
Committee chairman TBC Lalvenchhunga, Adviser to the Chief Minister, said the committee had been monitoring the project since its commencement. He said it was constituted by the government because of the project's scale and the need for coordination among several departments.
While describing the work completed so far as commendable, he said the pace of construction was slower than expected, primarily due to inadequate deployment of equipment and machinery by the contractor.
The contractor has already been instructed to speed up the work, he said, adding that the Project Implementation Unit (PIU) of the PWD, which oversees the project, should intensify its monitoring.
The committee comprises the Secretary of the Planning Department, Engineer-in-Chief of the PWD, Principal Chief Conservator of Forests of the Environment, Forest and Climate Change Department, Director of the Land Revenue and Settlement Department and the Aizawl Deputy Commissioner.
The Rs 500-crore project, funded under the PM-DevINE scheme of the Ministry of Development of North Eastern Region (DoNER), was sanctioned on February 10, 2024. The Mizoram PWD is the implementing and executing department, while the Planning and Programme Implementation Department is the nodal department.
The project was awarded to RG Buildwell, a Ghaziabad-based company, in December 2024 under the Engineering, Procurement and Construction (EPC) mode. Construction began in January 2025. According to PWD officials, financial progress stands at 31.49%.
The western bypass is the largest road project undertaken by the Mizoram PWD in terms of cost. It is designed to connect the ATL Road and Lengpui Road without passing through Aizawl city, diverting heavy vehicles away from the city and easing traffic congestion.
The road is also expected to reduce travel time between northern and southern Mizoram and facilitate economic development across the state. UNI ZS NST
More News

20 Nov 2026 | 12:00 AM

Aizawl, Nov 19 (UNI) Construction of the 45-km Aizawl Western Bypass Road has achieved 33.61% progress, with a government monitoring committee expressing concern over the slow pace of work and urging the contractor to deploy more machinery to expedite construction.

see more..

Cyclone Akvan to bring heavy rain to Kolkata, south Bengal on Friday

19 Nov 2026 | 11:47 PM

Kolkata, Nov 19 (UNI) With Cyclone Akvan changing its course, Kolkata and several districts of South Bengal are bracing for heavy rainfall on Friday.

see more..

Arunachal: ABKU seeks CM’s clarification over differing statements on Siang dam

19 Nov 2026 | 11:46 PM

Itanagar, Nov 19 (UNI) The Adi Baane Kebang United (ABKU) has sought a clear clarification from Chief Minister Pema Khandu over what it described as conflicting statements by ruling BJP leaders on the proposed Siang Upper Multipurpose Project (SUMP).

see more..

Arunachal minister inaugurates four education infrastructure projects in Shi-Yomi

19 Nov 2026 | 11:44 PM

Itanagar, Nov 19 (UNI) Arunachal Pradesh Education Minister Pasang Dorjee Sona on Thursday inaugurated four educational infrastructure projects in Shi-Yomi district, aimed at improving residential facilities and the learning environment for students in remote areas.

see more..

West Bengal Police transfers ICs of 50 police stations across the state

19 Nov 2026 | 11:43 PM

Kolkata, Nov 19 (UNI) The Inspectors-in-Charge (ICs) of several police stations across West Bengal have been transferred, according to a notification issued by the state police headquarters at Bhabani Bhawan on Thursday.

see more..