Haryana power utilities remove 4,222 redundant roadside poles

Panckula, Oct 14 (UNI) Haryana's power distribution companies have removed 4,222 redundant electricity poles from roadsides across the state, but 2,221 poles — more than a third of the 6,443 identified — remain standing, with the government setting a December 31 deadline to complete the drive aimed at eliminating unnecessary roadside obstructions and improving public safety.
The progress report reveals a sharp disparity between the two state-owned distribution utilities. Uttar Haryana Bijli Vitran Nigam (UHBVN) has completed over 91 per cent of its assigned work, while Dakshin Haryana Bijli Vitran Nigam (DHBVN) has removed less than a third of the redundant poles identified in its jurisdiction.
According to Managing Director Vikram Singh, UHBVN has removed 3,333 of the 3,651 poles identified, leaving 318 pending. DHBVN, however, has cleared only 889 of its 2,792 identified poles, with 1,903 still awaiting removal.
Overall, the two utilities have completed approximately 65.5 per cent of the statewide exercise.
Within UHBVN, the removal drive has been completed in the Ambala, Panchkula, Yamunanagar, Karnal and Kurukshetra circles. Among the circles reporting pending work, Kaithal has 57 poles awaiting removal, followed by Jhajjar with 35, Sonipat with 25 and Panipat with 22.
The removal exercise has been completed in DHBVN's Faridabad, Palwal, Gurugram-2 and Sirsa circles.
The statewide drive was initiated following a meeting chaired by Chief Minister Nayab Singh Saini in March, when concerns were raised over electricity poles that continued to occupy roadside spaces despite no longer serving an operational purpose.
The distribution companies were directed to identify such structures district-wise, dismantle them and deposit the recovered material in their respective stores in accordance with prescribed procedures.
The exercise is intended to clear unnecessary obstructions from roadsides, reduce potential safety hazards and improve the management of electricity distribution infrastructure.
Vikram Singh said progress was being reviewed regularly and the officials concerned had been instructed to ensure that the remaining work was completed by December 31.
With DHBVN accounting for nearly 86 per cent of the statewide backlog, the southern utility faces the bulk of the remaining work as the deadline approaches.
UNI KK RSA
More News

CBI seeks Punjab government files on transfers, CM office appointments, housing projects in corruption probe

14 Oct 2026 | 8:50 PM

Chandigarh, Oct 14 (UNI) The Central Bureau of Investigation (CBI) has sought original records relating to government transfers, appointments in the Punjab Chief Minister's Office, housing projects, procurement and licensing decisions as it widened its investigation into alleged corruption involving former Chief Ministerial aide Rajbir Singh Ghuman.

see more..

Election Commission caps voter deletion objections, warns of action against false applications

14 Oct 2026 | 8:23 PM

Chandigarh, Oct 14 (UNI) The Election Commission of India has imposed limits on applications seeking the deletion of names from electoral rolls, restricting individual voters to 10 objections during the claims and objections period and five per month during continuous electoral roll updation, in a move aimed at preventing frivolous complaints and protecting legitimate voters.

see more..

Punjab Police bust suspected cross-border drug network, arrest two with 7 8 kg heroin

14 Oct 2026 | 8:14 PM

Chandigarh, Oct 14 (UNI) Punjab Police have arrested two suspected drug traffickers, including a woman, and seized 7.823 kg of heroin in Pathankot district, uncovering what investigators believe is a cross-border smuggling network with suspected links to Pakistan, Director General of Police Gaurav Yadav said on Wednesday.

see more..

PM Modi to launch Rs 3,350-crore development projects in Ladakh on Thursday

14 Oct 2026 | 8:05 PM

Srinagar, Oct 14 (UNI) Prime Minister Narendra Modi will inaugurate and dedicate five development projects worth around Rs 3,350 crore in Ladakh on Thursday, including the new terminal at Leh airport, officials said.

see more..

Jhota's father calls for Punjab shutdown on October 15, demands CM, DGP resign

14 Oct 2026 | 8:03 PM

Chandigarh, Oct 14 (UNI) The father of slain anti-drug activist Parminder Singh Jhota on Wednesday called for a statewide shutdown on October 15, demanding the resignation of Punjab Chief Minister Bhagwant Mann and the Director General of Police, a CBI investigation into his son's murder and criminal proceedings against senior police officials.

see more..